John Wallace Middle School Project Building Committee approved construction invoices and authorized $490,042.86 in payment. The committee unanimously approved invoices from Enviromed Services for $46,507.50 and from SES for $1,200.50. Architect Bob Roach of Friar Architecture reported progress on
Permanent Municipal Building Commission · Meeting of April 2, 2026
CT NEWINGTON — John Wallace Middle School Project Building Committee approved construction invoices and authorized $490,042.86 in payment. The committee unanimously approved invoices from Enviromed Services for $46,507.50 and from SES for $1,200.50. Architect Bob Roach of Friar Architecture reported progress on punch list items, while Construction Manager Danielle Couture reported Phase II is on schedule with bathroom tile work underway, casework 75 percent complete, ceiling grids installed, and duct cleaning in progress.
Project Manager Henry Boers of CSG confirmed no state reimbursement issues or change orders have arisen. The architect is preparing for furniture, fixtures, and equipment selections.
In the full story:
- The complete report — 213 words
Source: the Permanent Municipal Building Commission meeting of April 2, 2026, compiled from the official minutes.
Members read the rest of this story and every Newington meeting we cover, in full.
Become a memberAlready a member? Sign inA 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms
Share this brief
Know someone in Newington who follows town government? Share Townbrief Newington: they can sign up free.